NAME OF PROJECT | PERMIT STATUS | REMARKS |
---|---|---|
3.0MW LINGOD HYDROPOWER PROJECT Brgy. Malinao, Gabaldon, Nueva Ecija | On going application of FPIC On going application of ECC | -At negotiation stage with IP for signing of MOA |
3.2MW ABACA HYDROPOWER PROJECT Brgy. Lipuga, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
8.0MW CASIGNAN HYDROPOWER PROJECT Brgy. Lipuga, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
2.4MW MANGAYNGAY HYDROPOWER PROJECT Brgy. Lipuga, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
4.88MW DENIP HYDROPOWER PROJECT Brgy. Cawayan, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
3.4MW LOWER TAAN HYDROPOWER PROJECT Brgy. Cawayan, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
3.5MW UPPER TAAN HYDROPOWER PROJECT Brgy. Cawayan, Alfonso Castañeda, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |
1.55MW DIAMAN HYDROPOWER PROJECT Brgy. Lukidnon, Dupax Del Sur, Nueva Vizcaya | FPIC MOA was signed on May 3,2018 DENR-ECC was approved LGU Endorsement was secured | -Waiting for the release of Certificate of Precondition |